PR-2404Atlas EnergySteady state

Grid Operations Analytics

Execution · FixedFee · Nov 10, 2025Jul 15, 2026

Project on track

All signals nominal.

Health drivers

Signals contributing to overall project health.

All signals nominal.

Financial health

Burn vs. plan, margin now and at completion.

Total budget
$3,400,000
Actual cost
$2,390,000
Planned value (BCWS)
$2,430,000
Earned value (BCWP)
$2,440,000
Estimate to complete
$950,000
Remaining budget
$1,010,000
Burn vs plan
98%
Current margin
2%
Forecast margin
2%
On plan

Team

Engagement leadership. Full allocations land with the resource service.

Client
Atlas Energy
Industry
Utilities
Account owner
Anika Söderberg
Partner
Anika Söderberg
Project manager
Oluwaseun Ade

Per-resource allocations and over/underutilization land with the resource-planning slice.

Delivery milestones

In-flight delivery milestones with PM-reported confidence.

No milestones recorded.

Risks & change events

Open risks and recent changes affecting scope, schedule, or staffing.

Open risks

No open risks.

Recent change events

  • Schedule
    Sprint review cadence shifted to bi-weekly
    Apr 18, 2026 · Reduced overhead

Leadership actions

Recommended interventions surfaced by health signals.

No interventions recommended this week.