Smart Factory Rollout — NA
Execution · FixedFee · Jul 15, 2025 → Dec 20, 2026
Project on track
All signals nominal.
Health drivers
Signals contributing to overall project health.
All signals nominal.
Financial health
Burn vs. plan, margin now and at completion.
- Total budget
- $8,900,000
- Actual cost
- $4,650,000
- Planned value (BCWS)
- $4,780,000
- Earned value (BCWP)
- $4,720,000
- Estimate to complete
- $4,250,000
- Remaining budget
- $4,250,000
- Burn vs plan
- 97%
- Current margin
- 1%
- Forecast margin
- 0%
On plan
Team
Engagement leadership. Full allocations land with the resource service.
- Client
- Ironwood Manufacturing
- Industry
- Industrial
- Account owner
- Devon Okafor
- Partner
- Devon Okafor
- Project manager
- Hiroshi Tanaka
Per-resource allocations and over/underutilization land with the resource-planning slice.
Delivery milestones
In-flight delivery milestones with PM-reported confidence.
No milestones recorded.
Risks & change events
Open risks and recent changes affecting scope, schedule, or staffing.
Open risks
- MediumPlant 3 readiness slippingSchedule · 60% likely · Cutover delays cascade
- MediumOT/IT integration complexity higher than estimatedDependency · 70% likely · +10% effort across plants
Recent change events
- SchedulePlant 3 cutover slipped 2 weeksApr 22, 2026 · +2 weeks
Leadership actions
Recommended interventions surfaced by health signals.
No interventions recommended this week.