PR-2409Vantage MediaWind-down

Audience Data Platform

Closeout · FixedFee · Apr 1, 2025May 30, 2026

Project on track

All signals nominal.

Health drivers

Signals contributing to overall project health.

All signals nominal.

Financial health

Burn vs. plan, margin now and at completion.

Total budget
$3,200,000
Actual cost
$2,980,000
Planned value (BCWS)
$2,990,000
Earned value (BCWP)
$3,010,000
Estimate to complete
$200,000
Remaining budget
$220,000
Burn vs plan
100%
Current margin
1%
Forecast margin
1%
On plan

Team

Engagement leadership. Full allocations land with the resource service.

Client
Vantage Media
Industry
Media
Account owner
Priya Raghavan
Partner
Priya Raghavan
Project manager
Cora Bellingham

Per-resource allocations and over/underutilization land with the resource-planning slice.

Closeout milestones

Closeout, knowledge transfer, and acceptance milestones.

No milestones recorded.

Risks & change events

Open risks and recent changes affecting scope, schedule, or staffing.

Open risks

No open risks.

Recent change events

  • Schedule
    Closeout review scheduled W22
    Apr 15, 2026 · On track for clean close

Leadership actions

Recommended interventions surfaced by health signals.

  • Medium
    Confirm redeployment plan for releasing resources.
    Project is winding down; releasing team should have next assignments confirmed.