Risk & Compliance Reporting Suite
Execution · FixedFee · Dec 1, 2025 → Oct 15, 2026
Project at watch
2 concerns: Budget, Risks.
Health drivers
Signals contributing to overall project health.
- MediumBudgetBurn 8% above plan.
- MediumRisks1 open High-severity risk.
Financial health
Burn vs. plan, margin now and at completion.
- Total budget
- $5,100,000
- Actual cost
- $2,690,000
- Planned value (BCWS)
- $2,490,000
- Earned value (BCWP)
- $2,460,000
- Estimate to complete
- $2,410,000
- Remaining budget
- $2,410,000
- Burn vs plan
- 108%
- Current margin
- -9%
- Forecast margin
- 0%
Watch
Team
Engagement leadership. Full allocations land with the resource service.
- Client
- Bluefin Capital
- Industry
- Asset Management
- Account owner
- Marcus Whitfield
- Partner
- Marcus Whitfield
- Project manager
- Oluwaseun Ade
Per-resource allocations and over/underutilization land with the resource-planning slice.
Delivery milestones
In-flight delivery milestones with PM-reported confidence.
No milestones recorded.
Risks & change events
Open risks and recent changes affecting scope, schedule, or staffing.
Open risks
- HighRegulatory schema change in Q3 — rework expectedSchedule · 80% likely · +4-6 weeks rework
- MediumClient SME availability inconsistentClient · 60% likely · Decision lag 1-2 weeks
Recent change events
- ScopeAdded Basel III reporting moduleApr 26, 2026 · +$280k effort
- StaffingCompliance SME added 50% allocationApr 20, 2026 · Specialist coverage
Leadership actions
Recommended interventions surfaced by health signals.
No interventions recommended this week.