Trial Master File Automation
Execution · FixedFee · Oct 1, 2025 → Jul 30, 2026
Project on track
All signals nominal.
Health drivers
Signals contributing to overall project health.
All signals nominal.
Financial health
Burn vs. plan, margin now and at completion.
- Total budget
- $2,800,000
- Actual cost
- $1,900,000
- Planned value (BCWS)
- $1,950,000
- Earned value (BCWP)
- $1,960,000
- Estimate to complete
- $900,000
- Remaining budget
- $900,000
- Burn vs plan
- 97%
- Current margin
- 3%
- Forecast margin
- 0%
On plan
Team
Engagement leadership. Full allocations land with the resource service.
- Client
- Helix Pharma
- Industry
- Life Sciences
- Account owner
- Priya Raghavan
- Partner
- Priya Raghavan
- Project manager
- Hiroshi Tanaka
Per-resource allocations and over/underutilization land with the resource-planning slice.
Delivery milestones
In-flight delivery milestones with PM-reported confidence.
No milestones recorded.
Risks & change events
Open risks and recent changes affecting scope, schedule, or staffing.
Open risks
No open risks.
Recent change events
No changes recorded in the last reporting period.
Leadership actions
Recommended interventions surfaced by health signals.
No interventions recommended this week.