PR-2416Atlas EnergyWind-down

Outage Prediction Models

Closeout · FixedFee · Aug 15, 2025Jun 15, 2026

Project on track

All signals nominal.

Health drivers

Signals contributing to overall project health.

All signals nominal.

Financial health

Burn vs. plan, margin now and at completion.

Total budget
$2,600,000
Actual cost
$2,100,000
Planned value (BCWS)
$2,180,000
Earned value (BCWP)
$2,200,000
Estimate to complete
$460,000
Remaining budget
$500,000
Burn vs plan
96%
Current margin
5%
Forecast margin
2%
On plan

Team

Engagement leadership. Full allocations land with the resource service.

Client
Atlas Energy
Industry
Utilities
Account owner
Anika Söderberg
Partner
Anika Söderberg
Project manager
Oluwaseun Ade

Per-resource allocations and over/underutilization land with the resource-planning slice.

Closeout milestones

Closeout, knowledge transfer, and acceptance milestones.

No milestones recorded.

Risks & change events

Open risks and recent changes affecting scope, schedule, or staffing.

Open risks

No open risks.

Recent change events

No changes recorded in the last reporting period.

Leadership actions

Recommended interventions surfaced by health signals.

  • Medium
    Confirm redeployment plan for releasing resources.
    Project is winding down; releasing team should have next assignments confirmed.