Tax Modernization Wave 2
Execution · FixedFee · Jul 1, 2025 → Dec 15, 2026
Project at watch
2 concerns: Budget, Risks.
Health drivers
Signals contributing to overall project health.
- HighBudgetBurn 21% above plan.
- MediumRisks2 open High-severity risks.
Financial health
Burn vs. plan, margin now and at completion.
- Total budget
- $12,300,000
- Actual cost
- $8,640,000
- Planned value (BCWS)
- $7,120,000
- Earned value (BCWP)
- $6,900,000
- Estimate to complete
- $4,400,000
- Remaining budget
- $3,660,000
- Burn vs plan
- 121%
- Current margin
- -25%
- Forecast margin
- -6%
Over budget
Team
Engagement leadership. Full allocations land with the resource service.
- Client
- Sequoia State Gov
- Industry
- Public Sector
- Account owner
- Anika Söderberg
- Partner
- Anika Söderberg
- Project manager
- Theo Marchetti
Per-resource allocations and over/underutilization land with the resource-planning slice.
Delivery milestones
In-flight delivery milestones with PM-reported confidence.
No milestones recorded.
Risks & change events
Open risks and recent changes affecting scope, schedule, or staffing.
Open risks
- HighLegacy mainframe extraction blocking 3 workstreamsDependency · 90% likely · 3-workstream cascade delay
- HighState agency leadership changeClient · 100% likely · Decisions paused for relationship rebuild
- MediumProcurement audit on critical pathDependency · 50% likely · Possible 2-week procurement freeze
Recent change events
- RiskAgency leadership change announcedApr 28, 2026 · Stakeholder reset
- ScheduleWave 2 release pushed 5 weeksApr 22, 2026 · +5 weeks
- ScopeMainframe shim added to scopeApr 15, 2026 · +$700k effort
Leadership actions
Recommended interventions surfaced by health signals.
No interventions recommended this week.