PR-2424Lumen University SystemRamp-up

Faculty Workload Analytics

Discovery · FixedFee · Apr 15, 2026Dec 30, 2026

Project on track

All signals nominal.

Health drivers

Signals contributing to overall project health.

All signals nominal.

Financial health

Burn vs. plan, margin now and at completion.

Total budget
$1,900,000
Actual cost
$70,000
Planned value (BCWS)
$90,000
Earned value (BCWP)
$85,000
Estimate to complete
$1,810,000
Remaining budget
$1,830,000
Burn vs plan
78%
Current margin
18%
Forecast margin
1%
On plan

Team

Engagement leadership. Full allocations land with the resource service.

Client
Lumen University System
Industry
Education
Account owner
Devon Okafor
Partner
Devon Okafor
Project manager
Nadia Volkova

Per-resource allocations and over/underutilization land with the resource-planning slice.

Readiness milestones

Kickoff, charter sign-off, and staffing readiness milestones.

No milestones recorded.

Risks & change events

Open risks and recent changes affecting scope, schedule, or staffing.

Open risks

No open risks.

Recent change events

No changes recorded in the last reporting period.

Leadership actions

Recommended interventions surfaced by health signals.

  • Medium
    Verify staffing readiness before start date.
    Ramp-up phase: confirm role coverage and start-date readiness.